adsense top

Friday, 10 January 2014

Civil engineering interview question set 1

1. Under what situation shall engineers use jacking at one end only and from both

ends in prestressing work?

During prestressing operation at one end, frictional losses will occur and the prestressing

force decreases along the length of tendon until reaching the other end. These frictional

losses include the friction induced due to a change of curvature of tendon duct and also the

wobble effect due to deviation of duct alignment from the centerline. Therefore, the

prestress force in the mid-span or at the other end will be greatly reduced in case the

frictional loss is high. Consequently, prestressing, from both ends for a single span i.e.

prestressing one-half of total tendons at one end and the remaining half at the other end is

carried out to enable a even distribution and to provide symmetry of prestress force along

the structure.

In fact, stressing at one end only has the potential advantage of lower cost when compared

with stressing from both ends. For multiple spans (e.g. two spans) with unequal span length,

jacking is usually carried out at the end of the longer span so as to provide a higher

prestress force at the location of maximum positive moment. On the contrary, jacking from

the end of the shorter span would be conducted if the negative moment at the intermediate

support controls the prestress force. However, if the total span length is sufficiently long,

jacking from both ends should be considered.

2. What is “preset” during installation of bridge bearings?

“Preset” is a method to reduce the size of upper plates of sliding bearings in order to save

the material cost. The normal length of a upper bearing plate should be composed of the

following components: length of bearing + 2 x irreversible movement + 2 x reversible

movement. Initially the bearing is placed at the mid-point of the upper bearing plate

without considering the directional effect of irreversible movement. However, as

irreversible movement normally takes place at one direction only, the bearing is

displaced/presetted a distance of (irreversible movement/2) from the mid-point of bearing

in which the length of upper plate length is equal to the length of bearing + irreversible

movement + 2 x reversible movement. In this arrangement, the size of upper plate is

minimized in which irreversible movement takes place in one direction only and there is no

need to include the component of two irreversible movements in the upper plate.

Note: “Preset” refers to the displacement of a certain distance of sliding bearings with respect to upper

bearing plates during installation of bearings.

3. In incremental launching method of bridge construction, what are the measures

adopted to enhance sufficient resistance of the superstructure during the launching

process?

(i) During the launching process the leading edge of the superstructure is subject to a large

hogging moment. In this connection, steel launching nose typically about 0.6-0.65

times span length is provided at the leading edge to reduce the cantilever moment.

Sometimes, instead of using launching nose a tower and stay system are designed

which serves the same purpose.

(ii) The superstructure continually experiences alternative sagging and hogging moments                                                                                during incremental launching. Normally, a central prestress is provided in which the


compressive stress at all points of bridge cross section is equal. In this way, it caters for

the possible occurrence of tensile stresses in upper and lower part of the cross section

when subject to hogging and sagging moment respectively. Later when the whole

superstructure is completely launched, continuity prestressing is performed in which the

location and design of continuity tendons are based on the bending moments in final

completed bridge condition and its provision is supplementary to the central prestress.

(iii)For very long span bridge, temporary piers are provided to limit the cantilever moment.

4. In bridge widening projects, the method of stitching is normally employed for

connecting existing deck to the new deck. What are the problems associated with this

method in terms of shrinkage of concrete?

In the method of stitching, it is a normal practice to construct the widening part of the

bridge at first and let it stay undisturbed for several months. After that, concreting will then

be carried out for the stitch between the existing deck and the new deck. In this way, the

dead load of the widened part of bridge is supported by itself and loads arising from the

newly constructed deck will not be transferred to the existing deck which is not designed to

take up these extra loads.

One of the main concerns is the effect of stress induced by shrinkage of newly widened

part of the bridge on the existing bridge. To address this problem, the widened part of the

bridge is constructed a period of time (say 6-9 months) prior to stitching to the existing

bridge so that shrinkage of the new bridge will take place within this period and the effect

of shrinkage stress exerted on the new bridge is minimized.

Traffic vibration on the existing bridge causes adverse effect to the freshly placed stitches.

To solve this problem, rapid hardening cement is used for the stitching concrete so as to

shorten the time of setting of concrete. Moreover, the stitching work is designed to be

carried out at nights of least traffic (Saturday night) and the existing bridge may even be

closed for several hours (e.g. 6 hours) to let the stitching works to left undisturbed.

Sometimes, longitudinal joints are used in connecting new bridge segments to existing

bridges. The main problem associated with this design is the safety concern of vehicles.

The change of frictional coefficients of bridge deck and longitudinal joints when vehicles

change traffic lanes is very dangerous to the vehicles. Moreover, maintenance of

longitudinal joints in bridges is quite difficult.

Note: Stitching refers to formation of a segment of bridge deck between an existing bridge and a new bridge.



Civil engineering interview question set 1

No comments:

Post a Comment